• Spray solutions further reading

    Last post : 1/8/2026

  • BETE Limited blog

    Last post : 1/29/2014

Case Study: Retrofitting a cleaning solution to rectangular, covered tanks with internal obstacles

Jan 2, 2026, 11:23 AM by Catherine Lees

 

THE SITUATION

An engineering firm contacted SNP for a StormBlaster™ cleaning system to retrofit a cleaning solution for a rectangular, covered storm tank at a wastewater treatment plant in Ireland. The project was part of a regional initiative to upgrade wastewater treatment facilities in collaboration with the area council.

The tank design presented unique challenges. It had two rectangular ‘cells’ of different lengths, one measuring 11.5 m x 8.8 m and the other 14.9 m x 8.8 m, with a number of walls/columns inside for structural support. In addition, there were large discharge pumps which had to be worked around. The customer wished to keep the number of StormBlasters to a minimum and to keep operating pressure as low as possible.


CHALLENGES

  • Internal Walls: Structural walls/columns within the tank caused shadowing, resulting in areas that were difficult to reach during cleaning.
  • Large Discharge Pumps: The placement of the pumps presented further obstructions which had to be taken into consideration.
  • Retrofit Constraints: The solution had to integrate seamlessly into an existing covered tank with minimal structural changes.
  • Cost: The customer wanted to keep the number of cleaning heads as low as possible.

THE SOLUTION

The presence of supporting columns inside the tank and the positioning of the pumps meant additional design considerations were required to ensure the StormBlaster heads were positioned optimally, allowing the jets to evenly reach every corner of the tank without any shadowing effects (where obstacles prevent jets from hitting the walls).

To address the challenges posed by the tank design, SNP developed a tailored cleaning strategy by dividing each tank into three virtual sections (see diagram on next page), each serviced by three dedicated 10 mm StormBlaster units to maximise cleaning efficiency. Cleaning heads were strategically positioned closer to obstructed regions and to improve coverage behind the large pumps.

This approach included extending the StormBlaster operation to a cycle and a half instead of a single cycle, ensuring that cascading water reached shadowed areas and effectively dislodged sludge. While small areas near internal wall units remained untouched due to shadowing, these limitations were acknowledged and accepted by the client.


THE PRODUCT

  • StormBlaster™
    • 6 StormBlaster units
    • 2 x 10 mm size nozzles
    • 316 stainless steel
    • Tested to 10 bar

RESULTS & CONCLUSION

SNP’s expertise and innovative use of StormBlaster technology enabled our client to retrofit the storm tank effectively. This solution not only addressed complex structural challenges but also aligned with the regional goals of modernising wastewater treatment infrastructure while maintaining cost and resource efficiency.

Benefits delivered:

  • Cost efficiency: Kept pressure and cleaning head count low, minimising operational costs.
  • Customisation: Tailored to the tank's specific dimensions and structural features.
  • Comprehensive cleaning: Effective removal of sludge despite challenges posed by walls and pumps.
  • Reduced water usage: Optimised cleaning cycles ensured minimal water wastage.

Download the pdf


 

Load more comments
New code
Comment by from

Share
 

Share |

BETE Blogs